Some Suggestions for Review of the Functioning of the Ministry of
Environment and Forests
Submitted to
Shri. T. R. Baalu
Hon'ble Union Minister for Environment and Forests
Government of India
On the occasion of
MoEF Regional Offices Meeting
23-24 October 2000
New Delhi
Submitted by
Environment Support Group ®
S-3, Rajashree Apartments, 18/57, 1st Main Road, S. R. K. Gardens,
Jayanagar, Bannerghatta Road, Bangalore 560 041. INDIA
Telefax: 91-80-6341977 Fax: 91-80-6723926 (PP)
Email: esg@bgl.vsnl.net.in
October 2000
Introduction
Environment Support Group is a non-governmental
organisation that is involved in working on social and environmental justice
issues of concern. It is an
interdisciplinary group involving experts from the areas of environmental law
and policy, planning, ecology, basic and social sciences and mathematics.
On 12 September 2000, Union Environment Minister
Shri. T. R. Baalu visited Bangalore, during which time a team from Environment
Support Group met with him. During the
discussions the Hon'ble Minister informed the ESG team of his plans of holding
a Regional Offices Meeting to review the environment/forest clearance
compliance. Based on this information,
the ESG team voluntarily decided to produce a Note examining the functioning of
the Ministry of Environment and Forests and highlighting areas for reform. The main purpose of this was to provide the
officials of the Ministry an external input to an internal evaluation process.
What we have attempted here is a synoptic view along
the following themes:
1.
The
Forest Clearance Cycle
2.
The
Environmental Clearance Cycle
3.
The
need for Decentralisation of the Clearance and Review Mechanism
4.
The
Emergent need for Scientific and Technical Capacity Building of the MoEF
5.
A
Submission of ESG to the Draft Industrial Siting Notification
These themes do not obviously comprehend the overall
scheme of review and monitoring of environmental and forest clearance
cycles. For the purposes of brevity
only pressing Issues of Concern underlining areas for reform are raised.
A brief gist of the existing Forest and
Environmental Clearance mechanisms are provided as Annexures towards the end of
this note, merely for the purpose of quick reference.
Theme 1: Forest Clearance
Cycles
Issues of concern to be
addressed:
1. Arbitrary Powers of
the DFO: The DFO of the State Forest Department (SFD)
has arbitrary powers, with no checks and balances whatsoever. Given
that the main verification of facts and site of project takes place at this
level, there is all possibility of political, administrative and personal
impressions forming a pressure lobby.
Quite possible that corrupt practices could be induced at this level,
say for instance by the investor, to secure a favourable decision. It is essential that this level of enquiry
is tightened, with public participation involvement, say through Public Hearing
Process, and the decision taken should be made public with reasons clearly
documented.
2.
Time
Targets at State Level of Clearance: There is no defined time set for processing and clearance
at the State level. This is a very weak arrangement
as in effect it means that the State can indefinitely delay the process of
clearance if it wants to. This is not
good administrative discipline. There
is a need to fix time period for the State Level clearance, with each sub-level
of clearance being provided their individual component of time. For instance it could be 30 days for the
DFO, 30 days for the PCCF and 30 days for the DFE to complete the formalities
and forward the proposal to Regional CCF/Central Office. In this way not only
is the Investor not harrassed, but as well there is a clear understanding of
where the decision is being taken at a particular point of time in the
clearance cycle. The only exception to
this strict adherence to effective and speedy clearance should be an "Act
of God" or similar incidents.
3. Empowering State
Levels of Clearance: When Project is rejected at the State level,
the Proposal is still forwarded to the Centre seeking endorsement of Rejection.
It is possible that
such a provision may have arisen due to the need to neutralise local political
backlash at the State level. This,
however, is a retrograde step as it involves unnecessary administrative
expenditure, involving the sparse resources of the MoEF. Considering the impetus on decentralisation,
State Governments should be confident of their stand.
4. Safeguarding
Protected Forests: The opinion of the Chief Wildlife Warden
(CWW) should be binding in cases involving protected forest areas, but are most
often not. In some cases, even when the
Chief Wildlife Warden (CWW) has rejected the proposal, the PCCF and the
Secretary DFE have recommended the proposal and forwarded the same to the
Centre without justification for overruling CWW's decision or providing higher
rationale for according approval. Eg.
Temporary mining clearance granted to M/s. Kudremukh Iron Ore Company Ltd. This approach is a bane to safeguarding the
country's fast depleting biodiversity.
5.
Integration
of Scientific opinion:
There is absolutely no scientific input in the entire process. When decisions to be taken become
increasingly complex given fragmentation of forests at a rapid rate, a
multitude of factors will have to be considered before taking a decision. Whilst there may be hundreds of applications
for small scales of forest clearances, there is often a few large projects that
in effect involve high levels of impact on the forests. Whether the scale of forest involved is
small or large, the day has arrived when even the tiniest patch is cleared for
"development" only after the most careful scrutiny. Given that, by and large, the DFO or RFO are
unable to be up-to-date with the latest understanding of forest systems, most
often due to large administrative workloads, it is imperative that a clear
scientific input should be integrated at the earliest stage of processing an
application. Not only will it enable
the formulation of a very sound decision, but will also prevent the unnecessary
administrative burden at higher levels were a project found not worth passing
the muster on scientific grounds.
6.
Need
for Public Involvement: There is absolutely no public
participation. When the EIA Notification
requires Public Hearings to be held for a schedule list of projects, those
projects that are not included in this list, yet having high impact, escape
public involvement in decision making as the Forest Clearance cycle completely
obviates the need for such engagement.
It would be a progressive step to make Public Hearings mandatory for all
projects involving forest clearances, thus covering the lacunae of the EIA
Notification. This fundamental
precaution is needed keeping in view the various Rights, esp. Rt to Livelihood
given the fact that there is a overwhelming dependence of minor forest
resources by forest dwelling communities for subsistence living.
Theme 2: Issues of concern in
the Environmental Clearance procedure
Issues of Concern to be
addressed:
Weak EIA process
1.
Poor
Quality of EIAs:
Perhaps the most critical area of concern with regard to the clearance
procedure is that the quality of information furnished by the project developer
as part of the EIA/EMP and DPR is often found wanting in crucial areas of the
project impacts. There have been
cases where EIAs have been completely fudged (Eg. Ernst and Young REIA for
Dandeli Dam), where the data furnished is unrepresentative to the area
(Eg. Air Pollution Modeling conducted
by Transoft of France for Tata Consultancy Services REIA of Mangalore Power
Company) and quite often there is a lot to be desired even in the fundamental
aspects presentation of facts and analysis of impacts.
2. Weak Technical
Competence of Consultants:
Given that the EIA is prepared by consultants hired by the developer/investor,
in most cases the EIA is viewed as a mechanism of compliance with procedures
and information provided is very superficial and often not representative of
the ground reality. This problem has
been widely acknowledged as undoing of the very precepts of the EIA
Notification. Despite which there is
very little or no verification of facts presented by conducting site visits or
ground verification.
3. Need for empanelling
Consultants:
Several suggestions have been offered over time to fix such lacunae. However, a most pressing need is to validate
Consultants, thus ensuring that in the very least the information brought is of
a quality that is justifiable for initiating the clearance process. The credentials of the Consultant/Consulting
Company/Organisation should be subject to public review as in the case of all
companies by way of furnishing Quarterly Report, Annual Reports, etc.
4. Need for Independent
EIA Authority: There is also the demand for setting up an
independent Environment Impact Assessment Authority headed by a judicial
officer and comprising of eminent scientists, technocrats and
environmentalists. Such a step must be
considered consciously and with due dispatch.
Faulty
environmental clearances
1. Pressure for Quick
Clearance:
The regulatory agencies at the State and Central levels are constantly under
pressure to accord quick clearance to the project, by a combination of investor
induced and bureaucratic and political interferences. Consequently, clearances are likely to be provided without
sufficiently addressing all the issues involved.
2. Technical Skills of
Review: Additionally,
in-house skills of review, from the scientific and legal points of view, have
been found wanting in a variety of areas, and exposed repeatedly, especially
through the process of Public Interest Litigation in different parts of the
country, and in several instances in the recent past, various Courts have
struck down final environmental clearances accorded, citing fundamental violations
in administrative review, planning and environmental legislation and lack of
application of mind on critical areas of environmental concern.
Rapid
EIA and Conditional Clearances
1. Rapid EIA: With the demand to accord speedy
clearances to industrial and infrastructure projects increasing, a mechanism
adopted by Pollution Control Boards and Ministry of Environment and Forests has
been to accord conditional clearances to projects merely on the basis of Rapid
Environment Impact Assessment. This is based
on one season data, which technically implies a 3-month period, but is normally
a one-month data. Again there is no
clear procedure to establish whether the data has been collected afresh or
collated secondarily. This effectively
provides an impression that some level of scientific work has been undertaken,
whereas in real terms the quality of the scientific methodology involved is
highly questionable.
2. Violation of
Conditions granted: Often, conditions are
violated blatantly and the violators get away scot-free with the Ministry of
Environment and Forests lagging in enforcing penal action against the violators
as per law. The immediate action that
needs to be taken for not fulfilling the conditions is that the environmental
clearance should be revoked. This is
not done in most cases and a classic example for this is the clearance accorded
to the 1,000 MW thermal power plant of Mangalore Power Company proposed to be
sited in the Dakshina Kannada region.
3. Quality of Conditions
Framed: A quick perusal of clearances granted by
MoEF to a variety of projects bring to light the typical terminology used in
defining conditions. Some examples are
listed: "carefully examined",
"strict compliance", "adequate facility", "regular
monitoring", "sufficient funds", "properly trained",
"appropriate measures to improve design and operating practices",
etc., etc. It may easily seen that none
of these terms can be considered as clearly defining a particular type action
that should be undertaken, which can be reviewed credibly based on existing
standards and most importantly can be held per law to penalise
non-compliance. Such conditions reflect
a lack of appreciation of the fundamental importance that clearances play in
mitigating environmental damage within the concepts of sustainable
development. Were such terms used
occasionally, it could have been ascribed to the lack of rigour on a few
officers in applying their minds to the task on hand. However, it is distressing to note that such terms are prevalent,
rather than rare, and are seen to be acceptable, than being questioned. This approach must be fundamentally revamped
and clear and specific conditions, even exhaustively describing the compliance
per existing standards, manuals, treaties, etc. should be the norm from
framing. The outcome of this will be
that monitoring mechanisms would be tightened and violations framed can be
easily defended in the Court of Law.
4. Monitoring Roles: Monitoring roles are exceptionally
important steps in ensuring that environmental degradation is mitigated,
especially in highly polluting industries.
Presently the Regional Office is mainly responsible for monitoring and
reporting to the Central Office.
However, the decision is taken at the Central level. This has time and again proved to be a
dis-jointed process as the Officer who has monitored is not empowered in
framing the conditions thereof and the officer framing the conditions has no
ground knowledge of the impacts. Quite
clearly in environmental compliance issues, there is simply no possibility of
critical evaluation based on secondary data and information. There is thus an immediate need to change
this process and empower the investigating officer in formulating follow-up,
rather than the existing scenario.
5. Compliance Reports: Presently a 6 monthly report of
compliance is to be filed by the project authority. This is made available to the public on demand. What action is taken thereafter is not subject
to public scrutiny. It would in the
best interest of maintaining local environment that the review and
recommendations following monitoring by the MoEF is also brought into the
public domain. This will not only
ensure a more benign reflection of the Ministry's creative interest in ensuring
transparency, but will also bring in public involvement with technical input
for better maintenance of local environment.
6. Clearance bloopers: There have been instances where quite a
few clearances granted have bloopers of a most interesting nature. The
clearance granted to the Almatti dam project is a classic case and contains the
following condition:
"3 (vi) Six monthly monitoring reports should be submitted to the Ministry
and its Regional Office, Chandigarh for review." And the very next
condition reads:
"4. Officials from Regional Office MoEF, Bangalore would be monitoring the
implementation of the environmental safeguards….". It is clear that the former condition may
have been an oversight, but quite strangely there are several clearances which
are marked by such blatant errors.
Almatti being in Karnataka, how Chandigarh comes into play is an issue
that could become legally embarrassing at a later date. What this reflects is that the such an important
task as issuing environmental clearance is often done in a very lackadaisical
manner.
Public
Hearing Process
1. Quality of
Information:
The 10th
April 1997 Amendment to the EIA Notification makes Public Hearings mandatory
for all projects listed in Schedule 1.
The process of calling for the hearing and the conduct of the same is
defined. If effectively utilised, this
could empower local populations tremendously in having some control over
decision making processes that directly impact them. However, a critical area of concern remains the quality of
information provided, as public has access only to the Executive Summary of the
project and that prepared by the developer, giving room for advocating one’s
project rather than making an objective statement of potential impacts. Further, given the low awareness of the
processes involved in industrial and infrastructural developments, the Public
Hearing process may end up as a mere formality, if no clear initiatives are
taken presently. There is a great role
for public interest advocacy agencies to play here and increase the level of
awareness of local populations and empower them with such information that
would enable them to make rationale choices.
2. Experience of Recent
Hearings: The experience from recent Public Hearings
is that the project developer and the agency conducting the hearing are
extremely secretive of the information.
The Executive Summary is often a brochure and contains little quality
information. People participating in
the Hearings are becoming disillusioned and often this is breeding conflict,
that very thing that Hearings sought to avoid.
Considering the present move to introduce the Right to Information,
there is clearly no need to make EIAs and related documents secretive as they
absolutely do not impinge on the security of the nation. An amendment to the Notification is thus
needed immediately to allow access to all detailed environmental information on
the project to ensure transparency, build public confidence, negate conflicts
and develop conditions with public input that is of a high quality.
3. Capacity Building: There is also an emergent need to train the
length and breath of this country in the conduct of and participation in Public
Hearings, including by developing modules and audio-visual programmes for
training, so this healthy process is evolved to maximum public interest
advantage.
4. Follow-up: The follow-up after the Hearing should also
be made available to the Public, for instance the report of the Public Hearing
panel. Also Hearings should be held
post clearance and post project implementation to ensure proper compliance and
develop confidence amongst the local community. World-wide, such healthy openness and engagement of local
communities has brought reputation to regulatory agencies and helped protect
the environment.
5. Widening the Hearings
Base: Public Hearings should also be made
applicable to project involving Forest Clearance and those with high impact that are not presently within the
purview of Schedule I. Eg.: Massive automobile units are not included,
though they have foundries and thus have major impacts. The Toyota Kirloskar factory at Bidadi near
Bangalore was cleared without Public Involvement even when the Special
Secretary of the Karnataka Dept of Environment had insisted the need for Public
Hearings.
Theme 3: Decentralisation of
the Clearance and Review Mechanism
Some Possible Steps
that could be adopted:
1. Improving Democratic
Involvement content: Perhaps a most critical feature that needs
to be addressed in the environmental clearance cycle is that the entire process
is initiated under bureaucratic control and is highly centralised. The process of conducting “Public Hearing”
is the only visible democratic intervention openly accessible to the public. Apart from a representation of local elected
representatives and leading citizens on the panel, there is no proviso for a
project and its impacts to be discussed and debated in local elected
bodies.
2. Integrating
Environmental Management with Local Government Involvement: The involvement of the public and rationalisation
of development projects and priorities has been provided for in the Town and
Country Planning Legislations, and more recently in the 73rd and 74th
Amendments. These enactments require a
very high degree of involvement within the planning processes by local
bodies. However, the set of
environmental legislations presently in force do not recognise this need
adequately. Most decisions are left to
the interpretation of regulatory agencies with no specific requirements for
integration of the local demands and concerns.
The existing mechanisms within the prevailing environmental clearance
cycle are largely exclusive of local government interventions and concerns,
despite the requirements for the same as per “enabling planning legislations”
(eg. Town and Country Planning Act) and those of local self government ( 73rd
and 74th Constitutional Amendments). In recognition of the principles laid down in the 11th
and 12th Schedule, therefore, it is essential that local governments
be an integral part of the environmental clearance cycle.
3. Devolving Powers: Considering that the Ministry has to comply
with the letter and spirit of the Constitutional 73rd and 74th
Amendments, it would be worthwhile to explore the possibility of evolving a
system of Regional Directorates to devolve powers of clearances and monitoring
at more local levels than is presently the case. Such Directorates should cover a range not as extensive as
present Regional Offices, but without increasing administrative burden should
work with State Regulatory agencies to evolve strong clearance and monitoring
discipline.
Theme 4: Scientific and
Technical Capacity Building of the Ministry of Environment and Forests
Preamble:
The functioning of
any administrative setup is effective only when there is a healthy system of
monitoring performance and promoting excellence. Government administrative setups are constantly attempting to
meet such standards. The Tiwari Committee
Report of 1980 envisaged a Technical
Department of Environment akin to the US EPA that would consist of technical
staff with the capacity to respond to the challenges of environmental
pollution, and natural resource management.
The enclosed article from Economic Times (published during 1997)
analyses how far the Ministry has achieved these goals.
The Ministry's
functioning today is in the least governed by the rationale set out by the
Tiwari Committee, and functions more along the dynamics between the four major
cadres of officers that man it. These
are the Civil Services, Forest Services, Secretarial Services and Scientific
Services. For instance the top decision
making rung of the Ministry ranging from the Secretary to the level of Under
Secretaries include about 25 officers from Civil Services, 25 officers from
Forest Services, 50 officers from the Scientific Services and rest are from
Secretarial Services in a total number of 150.
It may appear that the Scientific Services are considerable in number. However, the reality is somewhat different
as the key decision making officers are either from Civil Services or Forest
Services. Scientific opinion is by and
large advisory in nature and subservient to the compulsions placed by the
Administrators. For instance the
constitution of the National Coastal Zone Management Authority is a good case
in point.
Performance Review System:
In reviewing the
functioning of the Ministry, what is effectively in place is the
"Confidential Reporting" system, which forms the only basis of
monitoring progress and as well granting promotions. Here again there is problem in building the confidence of the
Ministry officials in their technical achievements as their review is
essentially effected by bureaucrats who have no significant background or capacity
to review the specialised skills and competence. Thus there is the tendency to underestimate the technical import
of the tasks on hand, and present the functioning of the Ministry in
administrative terms (say for instance number of clearances granted) than to
evaluate the quality of the functioning (that is to analyse whether the
existence of the Ministry has helped improve environmental quality in the
country).
Presently Governments
undertakes review of performance based on a five-point scale. This is essentially based on an archaic process
that has been by and large abandoned world-over, including in most progressive
government establishments, both in the developing countries and developed
nations as well.
The present process
of reviewing the Candidate's performance by Reviewing Officer is based on the
Reporting Officer's comments, and not on the basis of personal interaction or
interview with the Candidate. Further, it
is only a file transfer mechanism and there is no joint interaction between the
three officers. Fundamentally it must
be noted that the Reporting Officer who is mainly involved with Candidate whose
performance is being reviewed has absolutely no role in grading. This is a crucial gap as s/he is best suited
to evaluate the candidate having been interacting with him/her day in and day
out. Thus, to provide no power of
grading to this Reporting Officer gives rise to a variety of complex
problems. Some of them are listed
below:
1. Lack of Interaction
during Review: The Reviewing Officer who has the power to
grade operates in a vacuum, and has to rely either on the Reporting Officer's
entry in the CR or his/her own opinion formed based on hearsay. This would have been alright were the
Reviewing Officer closely interacting with the Candidate. However, it is not
clear if such interaction is taking place through regular personal meetings.
2. Lobbying of Better
Grading: In such a setup, there is tendency on part
of the candidates to please the Reviewing Officer and thus the Reporting
Officer could be sidelined, despite having the best knowledge on candidate's
performance. In cases of candidates who
would not resort to such questionable steps of influence, the possibility of
their review being attended to fairly will be marginal. Further, there is a major possibility of
unhealthy influences operating on the Reviewing Officer, and given the vacuous
situation in which s/he has to grade the candidate, it is very much possible
due to this systemic deficiency that the Grading is not necessarily reflective
of the reality.
3. Inter-cadre
inconsistencies: There has also been a convention in the
Ministry that Reviewing Officer has normally been from the Civil Services. There could be the possibility of the
Reviewing Officer being biased by inter-cadre disagreements leading to
inconsistencies in evaluation and reviews.
Thereby leading to a most unhealthy process that destroys administrative
discipline, develops cynicism and brings down the morale of the officers. A combination of these factors work to
inhibit the possibility of high levels of performances from officers.
4. Technical Competence
Review: There is very poor review of technical
competence of Candidates. Considering
that all Secretary level positions have been occupied from the Civil Services
(including Indian Administrative Service, Indian Postal Service, Indian Railway
Traffic Service, Indian Railway Accounting Service, Indian Audit Accounting
Service and Indian Revenue Service), the system of reviewing performance of
Technical Staff of the MoEF is thus left to Reviewing Officers who have no
qualifications for the same.
Apparently, civil service officers enter into the Ministry on the basis
of having had a background in science/engineering in their basic education. Certainly such knowledge basis, that has
over years become dated, must not form the basis for reviewing technical skills
in the apex body of the Government of India dealing with environment and forest
issues. In a country where industrial
operations are increasingly complex, industrial disasters frequent, and natural
disasters rampant, high technical skills are an essential prerequisite. It is only when technical officers are
reviewed by technically competent people, even if exterior, that the Ministry
will be able to guage whether it has the wherewithal to deal with the complex
task of monitoring, regulating and mitigating environmental pollution or
avoiding damage altogether. It may be
worthwhile to examine the possibility of establishing clear standards verifying
the technical and scientific competence growth areas of the candidate.
5. Poor Documentation: The Proforma for documenting performance
requires overhaul as it does not provide the scope or capacity for
comprehensive evaluation of the candidate.
It is merely a technical fix that is presently in place, and enables
quick entries lacking depth of review.
Several of the items forming the basis of the present evaluation
proforma are undefined and in some cases irrelevant.
6. Feedback of Review: There is no feedback to the candidate
providing details of assessment in order to encourage higher levels of
performance. Such a process is often a fundamental norm of any evaluation. To have completely steered clear of this
requirement develops an attitude of deference to higher authorities rather than
a climate of healthy criticism that is essential in a technical Ministry. A windows open approach enables the
candidate to identify strengths and weaknesses, provides a clearer
understanding to the Senior Officer to position the Division's performance more
appropriately and works together to build a Ministry that is competent and
responsive to the public need.
Capacity Building:
1. There
is an acute need to develop curricula, varying levels of training and evolve
modules for conducting periodic refresher courses with specialised topics to
bring the Officers of the Ministry on par with latest scientific understanding
of environment and pollution control technology. Such refresher courses should also involve administrative
management aspects and environmental law and policy awareness.
2. The
World Bank loan granted to Environmental Capacity Building project is
unfortunately not been utilised to develop such capacities, even when there
have separate categories to develop capabilities of Regional Offices and
Environmental Law, for instance.
Theme 5: Submissions vide MoEF Notification dated 21 June 1999 w.r.t.
Siting of Industrial Projects
Submitted: 20 August, 1999
Process of Review of Industrial Siting Applications,
suggested for inclusion:
1. Establishment
of new industrial units or expansion of existing units covered under Annexure I
and III of the notification, should be based on a comprehensive review by the
appropriate District Planning Committee (DPC), constituted per the
Constitutional (74th Amendement) Act, within whose jurisdiction the
investor proposes to locate the plant.
All information pertaining to the project should be made available for
review by the DPC.
(Explanation: Annexure 12 of the Constitution details a
list of items that provide local governments with review powers with regard to
Urban planning, regulation of land-use, water supply for industries,
infrastructure development, protection of environment and promotion of
ecological aspects, etc. The District
Planning Committee is proposed with the primary purpose of evolving planned
development and integrating local socio-economic developmental objectives in a
politically participatory and environmentally sustainable manner. As major industrial developments do
influence local development in a very significant manner, the most appropriate
forum of judging the advantages and disadvantages of a particular industrial
investment would be the DPC.
Importantly, it would provide impetus for decentralised decision making,
that which is advocated by the Panchayat Raj and Nagarpalika Acts.)
2. In
formulating its opinion, the DPC shall be assisted by an interdisciplinary
panel of experts constituted in consultation with the State Department of
Environment. The range of expertise to
be involved in the Expert Panel may follow the pattern of the Site Appraisal
Committee illustrated in Sec. 41 A of the Factories Act and also include a
Urban and Regional Planner, Social Scientist and Economist. The opinion formulated by the DPC must be
recorded in detail and without any exception whatsoever. The same shall be achieved prior to the
designate Environmental Public Hearing on the project called per the EIA
Notification.
(Explanation: As such industrial ventures involve highly
complex decisions, a progressive interaction amongst the various tiers of
governance is highly desirable.
Considering that the range is too large for the Union Ministry of
Environment to be involved directly in each and every siting decision, a
process of empowering Local and State Governments in the decision making cycle
is desirable. This would not only
lighten the burden of critically evaluating each project at the central level,
but would also increase chances for evolving a decision that is locally
acceptable. Considering that such decisions
would most necessarily require positive political and local community
responses, that which is secure in scientific rationale, the Expert Panel would
be an effective instrument of support.
The review by this forum prior to the Environmental Public Hearing will
enable a more informed debate in the Public Hearing, and as well enable a more
focussed discussion of critical concerns.)
3. The
DPC’s opinion on the project siting shall be placed for public comment and
review, along with all other detailed information on the project for the
purpose of conducting the designate Environmental Public Hearing. Public comments placed during or prior to
the hearing, should be documented without exception.
(Explanation: Enables transparency in decision making,
helps develop the quality of the decision, provides scope for conflict
resolution at local levels and prepares ground for progressive engagement
between the investor, local community, parastatal bodies, and the various tiers
of governance.)
4. A
Draft Final Report of the DPC pertaining to siting considerations shall be
prepared on the basis of the Public Hearing and shall contain clear and
qualified opinion with regard to the siting. The Final Report should once more
be placed for public review and a Public Hearing called to debate/discuss the
opinion produced. Necessary corrections
may be integrated, and further Hearings called if needed. Based on the evolved consensus, a final
decision with regard to the siting may be taken by the requisite authorities.
(Explanation: This would further build confidence and help
in completely resolving resident doubts.
It would guarantee transparency in decision making and thus probably
limit need for litigation.)
5. All
documents pertaining to the project should be available on demand for public
review at the offices of the local Panchayat/Nagarpalika. Only such information that directly
compromises proprietary interests may be excluded from public review.
(Explanation: Right
to Information will be enabled and accurate documentation will develop public
confidence in such review processes.
This would heighten chances for reduced conflicts on locational
aspects.)
Siting Criteria:
6. Industrial
Siting criteria should be in compliance with Part III of the National Building
Code of India pertaining to Development Control Rules and such other standards
evolved in the Code as may be relevant to the project in question.
(Explanation: This voluminous text of standards, endorsed
by the Bureau of Indian Standards Act, would enable a great many decisions
pertaining to industrial locations.
Such symbiotic arrangements would help evolve a sense of planned
development, and avoid repetitive legislation.)
7. Industrial
Siting must fully comply with local Town and Country Planning laws.
(Explanation:
For the simple reason that industrial location is primarily a question of land
use planning. Further, it would limit
chances for unplanned corridor development, occurrence of unplanned industrial
estate development, and improve chances for a coordinated development of
industrial townships.)
8. No
application for siting of industry included in Annexure I and III of this
notification should be considered in ecologically sensitive areas. Such areas must be defined on the basis of
the findings of the Expert Committee appointed by the Ministry vide its office
memorandum Dated 6.4.99 for identification of ecologically sensitive areas
which has been specifically empowered to detail:
1. Parameters for the identification of ecologically sensitive areas;
2. List ecologically sensitive areas; and,
3. Identify type of activities that may be allowed in such areas.
In view of such review in process, and based on the criteria evolved, State and
Local Governments must be directed to prepare a Register of Wetlands of
Importance and ecologically sensitive areas, in and around which there should
not be any industrial development allowed.
Such preparation may be done with constant engagement of local
educational and research institutions and the public at large.
(Explanation: Since it is an ongoing process of the
Ministry, it would be best to await the final report of this committee so there
is unity of thought between the proposed Annexure II items and those that will
be proposed by the aforementioned committee.
Given the extent of this country it would be an impossible task to
prepare such a list in short time. Thus
the process has to be ongoing, and can best be achieved if and only if local
and state Governments are involved in the exercise. A Register will help standardise information toward constantly
identifying sensitive habitats, and involvement of local expertise will enable
broad-basing of this extraordinary exercise.)
9. The
Advisory Committees of the Ministry pertaining to Industry, Infrastructure and
Thermal Power Plants must annually review Annexures I and III from the point of
view of expanding, restructuring and making the lists more comprehensive and
reflective of on-ground demands.
(Explanation: This would enable the Ministry to be
responsive to the latest evidence available on industrial location risks,
enable the evolution of planned development and most importantly, reflect a
constantly improving mechanism.)